HSR Layout Metro Station

Which line it is on, where it sits, when it might actually open, and what connects HSR Layout to the metro network in the meantime.

Last updated 11 August 2026 · HSR Stay neighbourhood guides

The HSR Layout metro station is not open. It is an elevated station on the Blue Line of Namma Metro, part of Phase 2A along the Outer Ring Road, and it is still under construction as at August 2026. BMRCL has said trial runs on the corridor begin in October 2026.

FactDetail
Station nameHSR Layout metro station
LineBlue Linenot the Yellow Line
PhasePhase 2A (Central Silk Board – Krishnarajapura)
StructureElevated, double track, two side platforms
LocationSector 6, HSR Layout, Bengaluru (12.91649°N, 77.63304°E)
Adjacent stationsCentral Silk Board on one side, Agara on the other
StatusUnder construction as at August 2026 — never opened
OpeningNo confirmed date. Originally June 2026, revised to around December 2026; trial runs targeted October 2026
OwnerBangalore Metro Rail Corporation Limited (BMRCL)
Current as at August 2026. Metro dates in Bengaluru move, and this one has already moved once. Every date below is attributed to whoever said it and when. Nothing here is a commitment by BMRCL, and none of it is advice to time a move around a station opening.

Is the HSR Layout metro station open?

No. As at August 2026 the HSR Layout metro station is under construction and has never carried passengers. Construction of the section it sits on — Reach 2A Package 1, a 9.859 km stretch — was awarded to Afcons Infrastructure on 13 October 2020.

If a listing, a broker or a blog tells you HSR Layout has metro connectivity today, they are describing something that has not happened yet. The nearest station you can actually board a train at is Central Silk Board, on the Yellow Line.

The station site sits in Sector 6. Sectors 5 and 6 are the two sectors closest to it, both about 0.3 km from their sector centre — our sector-by-sector guide measures the distance from all seven.

Which line is the HSR Layout metro station on?

The Blue Line. This is the single most commonly reported error about the neighbourhood, and it matters because the two lines go to completely different places.

Blue LineYellow Line
Has an HSR Layout stationYesNo
StatusUnder constructionOpen since 10 August 2025
Runs alongOuter Ring RoadHosur Road
RouteCentral Silk Board – Krishnarajapura, continuing to Kempegowda International AirportRV Road – Bommasandra
Length58.19 km overall; 19.6–19.75 km for Phase 2A19.15 km
Stations29 overall; 13 in Phase 2A16
Nearest station to HSR LayoutHSR Layout station itselfCentral Silk Board

Sources differ slightly on the length of Phase 2A — Wikipedia gives 19.633 km while press reporting commonly rounds it to 19.75 km. Both refer to the same Central Silk Board to Krishnarajapura corridor.

When will the HSR Layout metro station open?

No opening date is confirmed, and the published targets do not agree with each other. Here is every date currently in circulation, with who said it:

DateWhat it refers toStatus
June 2026The station's original target openingMissed — revised
Around December 2026The revised station opening, and the figure most widely quoted for HSR Layout, Bellandur and DoddanekundiNot met as at August 2026
October 2026BMRCL's stated start of trial runs on the Phase 2A corridor — not passenger serviceTargeted
End of 2026Press reporting on when the Silk Board – KR Pura section opensReported target
2027 / March 2027Passenger operations after clearance by the Commissioner of Metro Rail SafetyReported target

The gap between "trial runs in October 2026" and "passenger service in 2027" is not a contradiction — it is the normal sequence. Trains, signalling and power systems are tested first, then the Commissioner of Metro Rail Safety inspects the line, and only then can it carry passengers. How long that takes is the variable nobody publishes in advance.

The honest read. The HSR Layout station is close to physically finished but not open, the corridor enters testing around late 2026, and passenger service plausibly follows in 2027. If you are deciding where to live in Bengaluru, treat the metro as an improvement that arrives at some point rather than a commute you can plan around on a specific date.

Where exactly is the HSR Layout metro station?

The station is elevated, sits in Sector 6 of HSR Layout on the Outer Ring Road corridor, and is recorded at coordinates 12.91649°N, 77.63304°E. Wikipedia lists its address as AH45, Sector 6, Bengaluru 560034 — the 560034 pin belongs to neighbouring Koramangala, which is a common quirk of addresses along this stretch of the ring road.

It has two side platforms and double track. Trains run toward Central Silk Board in one direction and Agara in the other.

Which stations will the Blue Line connect HSR Layout to?

Phase 2A puts HSR Layout two stops from Silk Board and on the same line as most of the Outer Ring Road tech corridor. The 13 stations, in order:

#StationInterchange
1Central Silk BoardYellow Line
2HSR Layout
3AgaraRed Line (proposed)
4IbbaluruRed Line (proposed)
5Prestige Bellandur
6Embassy TechVillage Kadubeesanahalli
7Kodibeesanahalli
8Marathahalli
9ISRO
10Doddanekundi
11Bagmane Developers – DRDO Sports Complex
12Saraswathi Nagara
13Krishnarajapura (K.R. Pura)Purple Line · Indian Railways

For anyone working along the ORR, that list is the whole point. Embassy TechVillage, Bellandur, Marathahalli and Doddanekundi all sit on the same line as HSR Layout, with no interchange between them. Those are journeys that today mean the Outer Ring Road at rush hour.

The Blue Line does not stop at Krishnarajapura. Phase 2B continues for a further 38.557 km and 16 stations toward Kempegowda International Airport, with interchanges at Nagawara for the Pink Line and Hebbala for the Orange and Red Lines. Our guide to commuting from HSR Layout covers what each of those routes costs you by road today.

Will HSR Layout have more than one metro station?

Yes — two. Alongside HSR Layout station in Sector 6, Agara station is listed at Agara Village, 1st Sector, HSR Layout. It is also elevated, also under construction on Phase 2A, and is planned as an interchange with the proposed Red Line.

In practice that means the northern and southern ends of the layout each get their own station, rather than the whole neighbourhood funnelling through one entrance.

How do you reach the metro from HSR Layout today?

Via Central Silk Board, on the Yellow Line, roughly 1.5–2 km from the layout depending on your sector. The Yellow Line has been running since 10 August 2025 and covers 19.15 km from RV Road to Bommasandra across 16 stations.

Its service has improved steadily as rolling stock arrived:

FromPeak frequencyOff-peak
Opening, August 2025~25 minutes
November 202515 minutes
February 20269 minutes14 minutes
3 June 20267 minutes10 minutes

The June 2026 improvement came from BMRCL adding two Titagarh-built trainsets, taking the corridor to 10 active rakes. Trains run from about 5 am to 11 pm.

Going south from Central Silk Board, the Yellow Line reaches Bommanahalli, Hongasandra, Kudlu Gate, Singasandra, Hosa Road, Beratena Agrahara, Electronic City, Infosys Foundation Konappana Agrahara, Huskur Road, Biocon Hebbagodi and Delta Electronics Bommasandra. That makes Electronic City reachable by metro from HSR Layout today, provided you cover the first 1.5–2 km to Silk Board by auto, cab or bus.

Going north it reaches BTM Layout, Jayadeva Hospital, Ragigudda and RV Road, where it meets the Green Line.

When the Blue Line opens, Central Silk Board becomes a Blue–Yellow interchange, and an elevated walkway with a travelator has been reported as planned to link the two station boxes.

What will the metro actually change for HSR Layout?

Three things, and it is worth being precise about which:

  • The ORR corridor becomes a train ride. Bellandur, Embassy TechVillage, Marathahalli and Doddanekundi move from a traffic-dependent road journey to a fixed-duration one on a single line.
  • Silk Board stops being a bottleneck you must cross. Today, reaching the Yellow Line means getting to Silk Board Junction — widely reported as Bengaluru's second-most congested junction after Hebbal. A station inside HSR Layout removes that leg.
  • The airport gets a rail option, eventually. Phase 2B extends the Blue Line to Kempegowda International Airport, which is 45–50 km away by road. That is a later phase, not part of the Phase 2A opening.

What it does not change: the layout's internal geography. HSR Layout remains a place where getting from your street to the arterial road is a short auto or walk, and two stations do not make seven sectors walkable to a platform.

Common questions about the HSR Layout metro station

Is the HSR Layout metro station open?

No. As at August 2026 the HSR Layout metro station is under construction and has never carried passengers. It is an elevated station on the Blue Line, part of Phase 2A between Central Silk Board and Krishnarajapura.

Which line is the HSR Layout metro station on?

The HSR Layout metro station is on the Blue Line of Namma Metro, not the Yellow Line. This is the single most commonly reported error about the neighbourhood. The Yellow Line runs along Hosur Road and its nearest station to HSR Layout is Central Silk Board.

When will the HSR Layout metro station open?

No date is confirmed. The station was originally targeted for June 2026 and was revised to around December 2026. BMRCL has said trial runs on the Phase 2A corridor begin in October 2026, and press reporting in 2026 points to passenger service in 2027 once the Commissioner of Metro Rail Safety has cleared the line. Treat any specific date as a target, not a commitment.

What is the nearest working metro station to HSR Layout?

Central Silk Board, on the Yellow Line, is the nearest operational metro station to HSR Layout. It is roughly 1.5 to 2 km from the layout depending on your sector. The Yellow Line opened on 10 August 2025 and runs 19.15 km from RV Road to Bommasandra across 16 stations.

Will HSR Layout have more than one metro station?

Yes. Two Blue Line stations serve the layout: HSR Layout station, listed at Sector 6, and Agara station, listed at Agara Village, 1st Sector. Agara is also planned as an interchange with the proposed Red Line.

Can you reach Electronic City by metro from HSR Layout?

Yes, today, by first reaching Central Silk Board. The Yellow Line runs from Central Silk Board south along Hosur Road through Bommanahalli, Kudlu Gate and Hosa Road to Electronic City, Konappana Agrahara, Hebbagodi and Bommasandra. From 3 June 2026 it runs every seven minutes at peak and every ten minutes off-peak.

Which tech parks will the Blue Line connect HSR Layout to?

Phase 2A places HSR Layout on the same line as Prestige Bellandur, Embassy TechVillage Kadubeesanahalli, Kodibeesanahalli, Marathahalli, ISRO and Doddanekundi. Once open it becomes a single-line ride along the Outer Ring Road tech corridor with no interchange.

More HSR Layout guides

This page is part of our guide to living in HSR Layout. Also published:

Opening December 2026

Staying near the HSR Layout metro station?

HSR Stay is a serviced-apartment property opening in HSR Layout, Sector 6, in December 2026 — about 1 km from the upcoming HSR Layout metro station. Fully furnished 1 BHK and 2 BHK apartments for business travellers, relocating professionals and long stays. We are taking enquiries now.

Enquire on WhatsApp